CIP PROJECTS UNDER CONSTRUCTION
CIP Project NameProject TypeProject ManagerProject Status
Ager Rd. Green/Complete Streets ImprovementGreen/ Complete StreetSophady UongComplete (2 yr. Landscape Warranty)
Allison St. Levee ProjectDrainage ImprovementElizabeth McKinneyComplete (12 month Warranty)
Bowie Rd. Culvert ImprovementsCulvert RepairSophady UongComplete (12 month Warranty)
Calverton Blvd. Channel ImprovementsDrainage ImprovementTK Kim Complete (12 month Warranty)
Chillum Rd., Knollbrook Dr., Road Intersection CIP Project
Intersection Improvement
Elizabeth McKinney
Construction
Clear Creek Dr. Drainage ImprovementsDrainage ImprovementConstructionComplete (12 month Warranty)
Culvert Repair/Replacement Program - Nelson Perrie Rd. CulvertsCulvert ReplacementNawaf EsayedContract Ad and Award Process
Daisy Ln. Drainage ImprovementsDrainage ImprovementElizabeth McKinney
Complete (12 month Warranty)
Groveton Dr. Outfall ImprovementsDrainage ImprovementElizabeth McKinneyConstruction
Indian Head West Outfalls RepairDrainage ImprovementTK KimComplete (12 month Warranty)
Longfield Drainage StudyDrainage ImprovementNawaf EsayedContract Ad and Award Process
Marlboro Pk. Pedestrian Safety Improvements Ph. 1Pedestrian SafetySophady UongComplete (12 month Warranty)
Montpelier Dr. Green Street ImprovementsGreen / Complete StreetSophady UongComplete (12 month Warranty)
Owens Rd. Channel Drainage ImprovementDrainage ImprovementStephanie Walder Contract Ad and Award
Riverdale Park Channel Improvement
Drainage Improvement
Charlie GrifithConstruction
Sunnyside Ave. Bridge Replacement over Indian CreekBridge ReplacementElizabeth McKinneyComplete (12 month Warranty)
Tantallon Wall Repair
Roadway StabilizationTK Kim
Construction
Temple Hill Rd. Bridge Replacement over Pea Hill BranchBridge ReplacementTK KimComplete (12 month Warranty)
Vista Way, 408, Channel Drainage Improvements
Drainage Improvements
Charlie GrifithConstruction




CIP PROJECTS UNDER DESIGN
CIP Project NameProject TypeProject ManagerProject Status
Addison Rd. at Walker Mill Rd. Intersection ImprovementMajor RoadwayCaleb HiiFinal Design
BikeShare CIP ProjectBike FacilityStephanie WalderSemi-Final Design
Brandywine Rd. Bridge ReplacementBridge ReplacementJay ShahFinal Design
Campus Dr. Green Street ImprovementsGreen / Complete StreetUnmesh PatelPlanning
Chestnut Avenue Bridge over Newstop Branch, P-0115
Bridge ReplacementUnmesh PatelFinal Design
Clinton St. Storm Drain RepairDrainage ImprovementCharlie GriffithFinal Design
Harry S. Truman Dr. Green/Complete Streets ProjectGreen / Complete StreetTim RyePreliminary Design
Harry S. Truman Dr., Structure No. P-0581, Bridge ReplacementBridge ReplacementUnmesh PatelFinal Design
Largo Area CIP Roadway ProjectPedestrian SafetyUnmesh PatelFinal Design
Livingston Rd. Bridge Replacement over Piscataway CreekBridge ReplacementNawaf EsayedSemi-Final Design
Marlboro Pk. Pedestrian Safety Improvements Ph. 2Pedestrian SafetyCaleb HiiFinal Design
Marlboro Pk. Pedestrian Safety Improvements, Ph. 3
Pedestrian Safety
Caleb HiiPlanning
Metzerott Rd., MD 650 to Adelphi Rd., Pedestrian Safety ImprovementsPedestrian SafetyStephanie WalderFinal Design
Molly Berry Rd. Bridge ReplacementBridge ReplacementUnmesh PatelFinal Design
Old Landover Rd. Bridge ReplacementBridge ReplacementJay ShahPlanning
Race Track Rd. Pedestrian Safety ImprovementsPedestrian SafetyNoah DonoghuePlanning
Rhode Island Ave., Paducah Rd. to US 1, roadway project
Pedestrian Safety
Supreet RekhiPlanning
Ritchie Marlboro Rd., Brooke Ln., Intx Improvement CIP ProjectIntersection ImprovementStephanie WalderPlanning
Stuart Ln. Pedestrian Safety ImprovementsPedestrian SafetyNoah DonoghueSemi-Final Design
Temple Hill Rd. Culvert Replacement at Tinkers CreekBridge ReplacementNawaf EsayedPlanning