Do I need a permit to grade behind my yard? When is it necessary to have a Grading Permit?
Yes, a grading permit is required if you are grading more than 5,000 square feet of land or moving more than 100 cubic yards of...
Yes, a grading permit is required if you are grading more than 5,000 square feet of land or moving more than 100 cubic yards of...
You may apply for a Building or Grading Permit in the Momentum portal by entering the information directly into the County’s...
It takes approximately 3 months. Expedited processing is available if the permittee hires peer reviewers. Visit DPIE's website...
Depending on the size of the project, the response time to County comments and status of approvals from other agencies (M-NCPPC...
This table identifies key approvals needed.
Phase |
Prince George’s County DPIE | Prince George’s County SCD |