Driveways

General Information

  • A driveway permit is issued with a one year expiration date.
  • An extension is allowed with the payment of an extension fee.
  • Construction must meet County specs and standards.
  • Instructions for inspections are provided with the issued permit.
  • At least thirty (30) days is required after final acceptance of the permit work to receive refund of a cash bond.

Applying

For applicable forms visit Forms and Checklists.
Download Application for a Residential Driveway Entrance/Apron Permit

Applicant is required to bring in 3 copies of the Site/Plot Plan showing driveway location with dimensions. These drawings will be reviewed by Maryland-National Capital Park & Planning Commission, Department of Public Works & Transportation and a Structural Engineer.

  •  Four (4) Site/Plot Plans